Hi Guys,

Migrated our system from Ensemble 2014 to 2018 and but for some reason my tasks keep getting the attached error not sure why? 

 

Thanks

Product version: Ensemble 2018.1
Discussion (4)1
Log in or sign up to continue

A task expires if it can't run when it was scheduled. This could be because your Ensemble instance was down when the task started, or it could be because a previous instance of the task was still running when it was supposed to start again. For example, if you have a task set to run every minute but it takes the task 90 seconds to complete, then when it run at 12:00, it will be supposed to start again at 12:01, but since it will still be running, the 12:01 task will expire and the task will run again at 12:02.

No, it doesn't run as soon as the previous task ends. It runs at the next scheduled time. So in my example above, if your task runs at 12:00:00 and doesn't finish until 12:01:30, the next scheduled time is 12:02:00, so that's when it'll run next. I'm not sure how far back in versions this goes, but you might be able to change that behavior so it's more like what you're expecting.